NEW QUESTION 21
You have activated the workflow for confirmation variances in SAP Project System. Who is the receiver of this workflow item?
- A. The person responsible for the work center
- B. The person responsible for the superior WBS element
- C. The MRP controller for the network
- D. The person responsible for the network activity
Answer: C
NEW QUESTION 22
You have saved a network and activities with assigned material components. As soon as you release the network, you receive the error message "Business transaction cannot be carried out". What could be the reason for this error message?
- A. Missing material availability
- B. Missing authorizations to release material components
- C. Missing reservations for material components
- D. Missing budget for material components
Answer: B
NEW QUESTION 23
A customer needs to analyse the capacity requirements of their network activities. Which reports do you recommend? Note: There are 2 correct Answers to this question.
- A. Hierarchical reports
- B. Resource reports
- C. Structure information system reports
- D. Cost element reports
Answer: C
NEW QUESTION 24
Budgeting is implemented for projects. The budget has been adjusted several times. What standard report type provides an overview of adjustments on the budget?
- A. Structure overview for budgets
- B. Cost element report on budget updates
- C. Line item report for budgets
- D. Hierarchical report on budget updates
Answer: C
NEW QUESTION 25
What could be a reason to use expert mode in the valuation method for results analysis?
- A. Assignments of different accounts for postings to financial accounting
- B. Usage of different line IDs
- C. Billing WBS elements belonging to different company codes
- D. Valuation in different currencies
Answer: A
NEW QUESTION 26
Which of the following statements apply to project versions? Note: There are 2 correct Answers to this question.
- A. Project versions can be created automatically based on user status.
- B. Manually created project versions always require a project version profile.
- C. Project versions are mandatory for Milestone Trend Analysis (MTA).
- D. Project versions can be changed.
Answer: C,D
NEW QUESTION 27
Which statements describe planned and actual revenue for WBS elements? Note: There are 2 correct Answers to this question.
- A. Planned revenue can be transferred from a sales quotation.
- B. Actual revenue is posted via a billing plan assigned to a WBS element.
- C. Planned revenue requires a sales order assigned to a WBS element.
- D. Actual revenue is posted via a billing document created from a sales order
Answer: A,D
NEW QUESTION 28
A service company uses project management and they complain that the system does not prevent their project managers from exceeding their budgets. What actions do you have to take to solve the problem?
- A. Activate availability control for projects in the controlling area. Enter the plan data for each WBS element.
- B. Activate availability control for the WBS elements. Define the tolerance limits on each WBS element.
- C. Activate commitment management in the project definition. Enter the budget in the master data of the top WBS element.
- D. Activate availability control in the assigned budget profile. Define the tolerance limits in customizing.
Answer: D
NEW QUESTION 29
You want to use subnetworks during the project. Which of the following statements describes subnetworks?
- A. A subnetwork cannot be defined for a superior subnetwork.
- B. Subnetworks must be scheduled separately from the superior network.
- C. The scheduling type of a subnetwork is always copied from the superior network.
- D. Maintenance orders can be defined as subnetworks.
Answer: D
NEW QUESTION 30
You are using budgeting and active availability control. How can availability control be activated? Note:
There are 2 correct Answers to this question.
- A. Automatic activation with the first actual posting
- B. Automatic activation with budget assignment
- C. Background activation (CJBV - Activate Availability Control)
- D. Automatic activation with assignment to an investment program
Answer: B,C
NEW QUESTION 31
How can you record external service activities with service master data? Note: There are 2 correct Answers to this question.
- A. Create a service entry sheet.
- B. Confirm the network activity for external services.
- C. Post a goods receipt in the goods movement application (MIGO).
- D. Confirm the activities in the Cross-Application Time Sheet (CATS).
Answer: A,D
NEW QUESTION 32
What functionality can you perform with activity elements?
- A. Schedule WBS elements
- B. Assign work centers and capacities
- C. Assign material
- D. Create relationships
Answer: D
NEW QUESTION 33
Which object is used to allocate the costs from a claim to the project structure?
- A. WBS element
- B. Network activity
- C. Claim
- D. Internal order
Answer: D
NEW QUESTION 34
You used reductions to reduce the scheduled duration of all internally-processed activities in your project. However, the duration did not changed after overall network scheduling.
What do you check? Note: There are 2 correct Answers to this question.
- A. If the reduction strategy is set in each activity
- B. If the reduction strategy is set in the network header
- C. If the maximum reduction level is less than 100
- D. If the appropriate reduction type is set in the parameters for network scheduling
Answer: B,D
NEW QUESTION 35
Which of the following apply to dynamic item processor (DIP)? Note: There are 3 correct Answers to this question.
- A. DIP is used to create a quotation.
- B. Material determination is mandatory.
- C. Sales prices are maintained in the DIP profile.
- D. Usage of cost elements is mandatory.
- E. Sources can be based on line items.
Answer: A,C,E
NEW QUESTION 36
The basic dates of subordinate WBS elements should be extrapolated without taking into account the basic dates of higher-level WBS elements. What planning method for basic dates do you use?
- A. Top-down
- B. Bottom-up
- C. Strict bottom-up
- D. Free planning
Answer: B
NEW QUESTION 37
How can you update the degree of processing for an activity?
- A. By using results analysis
- B. By confirming the activity
- C. By changing the activity
- D. By scheduling the activity
Answer: B
NEW QUESTION 38
......