
[Sep 26, 2023] SPS Exam Dumps PDF Guaranteed Success with Accurate & Updated Questions
Pass SPS Exam - Real Test Engine PDF with 164 Questions
NEW QUESTION # 44
Trunk-based branching strategy and common build and test instances will help the teams discover issues early. True or False?
- A. FALSE
- B. TRUE
Answer: B
NEW QUESTION # 45
As part of the Nexus Sprint Retrospective, the team should address if there is technical debt in the product. True or False?
- A. FALSE
- B. TRUE
Answer: B
NEW QUESTION # 46
In Nexus, an increment is considered DONE only when it is integrated, usable and potentially releasable. True or False?
- A. FALSE
- B. TRUE
Answer: B
NEW QUESTION # 47
Who participates in Nexus Daily Scrum?
- A. All the Nexus Members
- B. Scrum Masters & Team leads
- C. Product Owner, Scrum Master & Integration team
- D. Appropriate representatives from individual Scrum Teams
Answer: D
NEW QUESTION # 48
Who coaches and guides the Scrum Team in the application of Nexus?
- A. Scrum Integration Team
- B. Project Manager
- C. Product Owner
- D. Nexus Integration Team
Answer: D
NEW QUESTION # 49
The Nexus Team has failed to meet the Nexus Sprint Goal for two sprints in a row.
What are the possible reasons for this? (Select two best answers)
- A. Nexus Integration Team is not coordinating the work among the developers
- B. Developers are struggling to integrate their work
- C. Definition of Done has too stringent
- D. There is technical debt in the product
Answer: B,D
NEW QUESTION # 50
Who is not allowed to participate in Nexus Daily Scrum?
- A. NIT members
- B. Scrum Master
- C. Stakeholders
Answer: C
NEW QUESTION # 51
What is the purpose of the Nexus Sprint Retrospective?
- A. To identify issues that have affected more than one team
- B. To craft the Sprint Goal
- C. To refine the product backlog
- D. To decide on how the remaining retrospective should be conducted
Answer: A
NEW QUESTION # 52
How much refinement is needed for Product Backlog items?
- A. Until the Product Backlog item is discussed in 3 different sessions
- B. Until the Product Backlog Items are sufficiently independent to be worked on by a single Scrum Team without excessive conflict
- C. Until the Stakeholders are satisifed
Answer: B
NEW QUESTION # 53
Which are the three valid questions that can be discussed during Nexus Daily Scrum?
- A. Was the previous day's work successfully integrated?
- B. What did I do yesterday towards Sprint Goal?
Answer: A
NEW QUESTION # 54
Select the activities performed during the Cross-Team Refinement.
- A. Assign product backlog items to each team
- B. Decompose backlog items
- C. Identify which team is likely to work on that item
- D. Identify areas for improvement
- E. Identify the dependencies between items
Answer: B,C,E
NEW QUESTION # 55
One of the key stakeholders sends an email to NIT Scrum Master. He is requesting the Nexus Sprint Review to be planned for 5 hours instead of 4, because the team is unable to demonstrate all the developed features.
What should the Nexus team do next?
- A. Disagree, because Nexus framework does not allow the Nexus Sprint Review to be longer than 4 hours
- B. Agree, because stakeholders have a right to see every feature developed
- C. Discuss internally to evaluate if indeed 5 hours are necessary before responding to stakeholder
Answer: C
NEW QUESTION # 56
Adding additional resources to Nexus will result in the value that is being delivered. True or False?
- A. TRUE
- B. FALSE
Answer: B
NEW QUESTION # 57
Every team member of all the Scrum Teams must attend the Cross-Team Refinement event. True or False?
- A. TRUE
- B. FALSE
Answer: B
NEW QUESTION # 58
You are working in a Nexus with 3 teams. During the Nexus Sprint Planning, teams ran out of refined product backlog items. The items selected so far can only consume half of the Sprint.
What should the Nexus team do?
- A. Cancel the Sprint
- B. Pause the Sprint Planning and initiate the Cross-Team Refinement meeting so that more items are available for teams to pick up the work
- C. Conclude the Sprint Planning meeting
Answer: C
NEW QUESTION # 59
Can a specialist outside of Nexus join Nexus Integration Team? Yes or No?
- A. No
- B. Yes
Answer: B
NEW QUESTION # 60
Who are the members of Nexus Integration Team? Select all that apply.
- A. Scrum Master
- B. Scrum Team members
- C. Project Manager
- D. Product Owner
- E. Customer
Answer: A,B,D
NEW QUESTION # 61
What is the purpose of Nexus Sprint Backlog? Select two best answers
- A. To provide a view of work that is not part of the product backlog
- B. To list all the work that is being performed by the Nexus Integration Team
- C. To make the dependencies transparent
- D. To highlight the flow of work during the Sprint
Answer: C,D
NEW QUESTION # 62
......
Get New SPS Certification Practice Test Questions Exam Dumps: https://www.actualtestsquiz.com/SPS-test-torrent.html
Real SPS Exam Dumps Questions Valid SPS Dumps PDF: https://drive.google.com/open?id=16h3iqwikGj4A4gy484Ox9aZSqDpu3AdK

