C_ACTIVATE12 Exam Dumps Pass with Updated 2021 Certified Exam Questions
C_ACTIVATE12 Exam Questions - Real & Updated Questions PDF
What is the expense of Certified Associate - SAP Activate Project Manager
The expense of Certified Associate - SAP Activate Project Manager is $250.
- Number of Questions: 80
- Passing Score: 63%
- Format: Multiple decisions, numerous answers
- Length of Examination: 180 minutes
Understanding valuable and specific pieces of Certified Associate - SAP Activate Project Manager
The going with will be discussed in SAP C_ACTIVATE-12 dumps:
- Conversion for SAP SAP HANA
- SAP Activate Overview
- SAP Activate well overall
- Aspects to be considered for establishing SAP Fiori as a segment of your execution
- SAP Activate personally
- SAP HANA On-Premise
- Scope and Goals of ACT100
- Implement SAP HANA On-Premise
- Implement SAP HANA Cloud
- Landscape Transformation
- Landscape Transformation for SAP SAP HANA
- Factors affecting SAP Activate
- System Conversion for SAP SAP HANA
- Aspects to be considered for inciting SAP Fiori as an element of your execution
- SAP Activate Overview
- Workstreams personally
NEW QUESTION 20
Identify the two landscape transformation specific tasks in the explore phase.
There are 2 correct answers to this question.
Response:
- A. Perform Client transfer
- B. Setup Landscape Transformation Software
- C. Define the Data Migration Architecture
- D. Run a Landscape Transformation Assessment
Answer: B,D
NEW QUESTION 21
Which of the following are available in the initial SAP Methodologies JAM Page?
There are 2 correct answers to this question.
Response:
- A. Accelerators
- B. Roadmaps
- C. Task description
- D. Summary
Answer: A,B
NEW QUESTION 22
In Which phase does the Transition toOperations work stream start?
Please choose the correct answer.
Response:
- A. Prepare
- B. Deploy
- C. Explore
- D. Realize
Answer: B
NEW QUESTION 23
What are someof the capabilities end users can utilize to adapt and change their launchpad home page according to the way they work?
- A. Add a new group
- B. Rearrange or move tiles within a group
- C. Delete a predelivered group
- D. Add any SAP Fiori apps to a group, regardless of role
- E. Rename a predelivered tile
Answer: A,B,E
NEW QUESTION 24
In which phase do you verify that the SAP Best Practices content meets the customer's business needs, and then capture gaps?
Please choose the correct answer.
Response:
- A. Prepare
- B. Deploy
- C. Explore
- D. Realize
Answer: C
NEW QUESTION 25
What information does the product team need so that they can estimate the relative size of backlog user story correctly?
Please choose the correct answer.
Response:
- A. Definition of Done
- B. Test strategy
- C. Overall project schedule
- D. Available project resources
Answer: A
NEW QUESTION 26
What tool provides sizing estimators for the "system conversion" transition path?
- A. SAP best practices explorer
- B. Scope and effort analyser
- C. SAP readiness check
- D. SAP Transformation navigator
Answer: C
NEW QUESTION 27
Which new project roles are introduced with the SAP Activate Methodology for the Agile delivery approach?
There are 2 correct answers to this question.
Response:
- A. Design Thinking Coach
- B. Product Owner
- C. Integration Lead
- D. SCRUM Master
Answer: B,D
NEW QUESTION 28
When is provisioning of the production system requested?
- A. After the starter system is decommissioned
- B. After completing configuration of the business processes in thequality system
- C. Immediately after receiving the active quality system
- D. Immediately after receive the inactive quality system (Preset phase)
Answer: C
NEW QUESTION 29
What is a strategy level 0(L0) artifact?
- A. Optional information that is NOT important for project activities
- B. Preliminary strategy developed by the customer to approach the project in a specific workstream
- C. Approach document that is developed by a united project team (partner+ customer)
- D. Project result that is developed solely by the partner
Answer: B
NEW QUESTION 30
What are some characteristics of SAPS/4HANA Cloud?
- A. SAP S/4HANA Cloud is multi-tenant, meaning your service runs in a shared environment.
- B. SAP S/4HANA Cloud provides additional functionality for customers that require broad extensions and deep configuration capabilities.
- C. SAP S/4HANA Cloud includes quarterly innovation cycles.
- D. SAP S/4HANA Cloud is single-tenant; meaning your service runs in a dedicated environment.
- E. SAP S/4HANA Cloud runs in an infrastructure with private, managed services for SAP solutions.
Answer: A,C
NEW QUESTION 31
What do you do during Sprint Execution?
Please choose the correct answer.
Response:
- A. Hold a retrospective at the endof each week
- B. Present status of selected user stories in the sprint scope on a scrumboard
- C. End a sprint when the sprint backlog items are all complete
- D. Measure the sprint progress with a percentage complete report
Answer: D
NEW QUESTION 32
What are some responsibilities of the Business Process Expert in SAP S/4HANA Cloud implementation projects?
- A. Expert in solution processes and configuration
- B. Guides the system configuration
- C. Drive decisions and perform testing
- D. Performs and confirms configuration
Answer: C,D
NEW QUESTION 33
What types of extensibility are supported directly in the SAP S/4HANA Cloud solution?
- A. Side-by-Side Extensibility
- B. Managed Extensibility
- C. In-App (Key User) Extensibility
- D. Classic Extensibility
Answer: B,C
NEW QUESTION 34
Which of the following is not correct about workstreams?
There are 2 correct answers to this question.
Response:
- A. Workstreams are dependent on phase start and end
- B. It is assigned as an attribute to phases, deliverables and tasks
- C. It is a collection of related deliverables
- D. It can span phases
Answer: A,B
NEW QUESTION 35
What are some of the key characteristics of the implementation approach in SAP Activate Methodology?
There are 3 correct answers to this question.
Response:
- A. Delta-based
- B. Fixed scope
- C. Cloud Ready
- D. Based on Ready-to-use Content
- E. On premise only
Answer: A,C,D
NEW QUESTION 36
What is the correct order of the SAP Activate Methodology phases?
Please choose the correct answer.
Response:
- A. Plan -> Design -> Build -> Operate
- B. Plan -> Build -> Run -> Sustain
- C. Prepare -> Discover -> Explore -> Realize -> Deploy -> Run
- D. Discover -> Prepare -> Explore -> Realize -> Deploy -> Run
Answer: D
NEW QUESTION 37
......