NEW QUESTION 36
What happens to the expense line after it is processed?
- A. Nothing significant results.
- B. The actual cost is recorded at the portfolio level.
- C. The actual amount incurred becomes part of the cost plan.
- D. The cost plan closes.
Answer: C
NEW QUESTION 37
Which of the following are true regarding how the My Project Space (Project Workspace) handles dynamic content? (Choose two.)
- A. If the project state is Pending or Open, planned start date and planned end date are displayed.
- B. If the project state is On Hold, actual start date and actual end date are displayed.
- C. If the project state is Draft, actual start date and actual end date are displayed.
- D. If the project state is Work in Progress, actual start date and planned end date are displayed.
Answer: A,D
NEW QUESTION 38
What role can configure an idea module, map idea categories to the idea module, and add navigation for the Idea Portal?
- A. Demand manager [it_demand_manager]
- B. Project manager [it_project_manager]
- C. Idea admin [idea_admin]
- D. Idea manager [idea_manager]
Answer: C
NEW QUESTION 39
Which roles can modify agile properties? (Choose two.)
- A. admin.
- B. scrum_master.
- C. it_pps_admin.
- D. product_owner.
Answer: A,C
NEW QUESTION 40
Which of the following states appear in the process flow indicator at the top of the Demand form by default?
(Choose three.)
- A. Updated
- B. Draft
- C. Screening
- D. Approved
- E. Deferred
Answer: B,C,D
NEW QUESTION 41
Who can submit Ideas?
- A. Any IT user.
- B. Any ITIL user.
- C. Any user.
- D. Any demand user.
Answer: C
NEW QUESTION 42
Demand managers can enhance a demand request by adding the following: (Choose three.)
- A. Problems
- B. Decisions
- C. Requirements
- D. Stakeholders
- E. Change Requests
Answer: B,C,D
NEW QUESTION 43
To use the Time Sheet dashboard, what plugin must be installed?
- A. Employee Service Center (com.sn_hr_service_portal)
- B. Common ITSM Service Portal Application Components (com.snc.app_common.service_portal)
- C. Performance Analytics - Content Pack - PPM Standard plugin (com.snc.pa.pmo_dashboards)
- D. Knowledge Management - Service Portal (com.snc.knowledge_serviceportal)
Answer: C
NEW QUESTION 44
A project expense line is a cost associated with a specific source. Examples of specific sources could include:
(Choose three.)
- A. Demand.
- B. Project.
- C. Fixed Asset.
- D. Configuration Item (CI).
- E. User.
Answer: C,D,E
NEW QUESTION 45
If the Agile Development 2.0 plugin is activated, an idea can be converted into which of the following task types? (Choose three.)
- A. Epic
- B. Project
- C. SAFe feature
- D. SAFe epic
- E. Story
Answer: A,B,E
NEW QUESTION 46
The information displayed on Project Workspace is setup in which table?
- A. pm_home_page_card
- B. vtb_card
- C. vtb_card_history
- D. pm_project
Answer: A
NEW QUESTION 47
Where do you define 'Roles' requested via resource plans?
- A. No need to define it differently, they are same are system roles
- B. Resource roles under resource management.
- C. Roles under system security
- D. Under skill management modules
Answer: B
NEW QUESTION 48
The PPM Standard plugin enables an it_project_manager to perform the following activities: (Choose three.)
- A. Define target for the portfolio
- B. Establish resource requirements and track costs.
- C. Track actual amount spent compared to an approved budget.
- D. Configure cost type definition
- E. Determine overall project cost requirements
Answer: B,C,E
NEW QUESTION 49
When creating a resource plan within a demand, how are the default dates on a resource plan determined?
- A. Using demand created date
- B. From portfolio date
- C. Resource plan(s) cannot be created from demand
- D. From demand start date and due date
Answer: D
NEW QUESTION 50
A customer requires five (5) teamspaces to support different departments. What should you do?
- A. Activate via each teamspace plugin.
- B. Enable the teamspace property.
- C. Contact the Account Representative to activate the teamspaces.
- D. Use UI Policies and Business Rules to enable teamspaces.
Answer: A
NEW QUESTION 51
The Project Portfolio Management application supports domain separation at this level:
- A. Data only
- B. Level 1 - Tenant data management
- C. Level 3 - Tenant self-managed configuration
- D. Level 2 - Tenant process management
Answer: A
NEW QUESTION 52
This should be updated by an it_pps_admin, so that the stakeholder list will automatically populate when a user creates a demand or project.
- A. Stakeholder registry.
- B. Application registry.
- C. Demand form.
- D. Project form.
Answer: A
NEW QUESTION 53
Which plugin provides a layer of artificial intelligence that empowers features and capabilities across applications to provide better work experiences?
- A. Predictive Intelligence for PPM [com.snc.ppm_ml]
- B. Strategic Spend Tracking for PPM [sn_ppm_sst]
- C. Scenario Planning for PPM [sn_pw_scenario]
- D. PPM Standard [com.snc.financial_planning_pmo]
Answer: A
NEW QUESTION 54
How is a resource group's capacity derived for resource planning?
- A. Stored with Group Record.
- B. Stored in Resource_Allocation_Daily table.
- C. Aggregate capacity of all its members.
- D. Stored in Resource_Aggregate_Daily table.
Answer: C
NEW QUESTION 55
......