NEW QUESTION 36
What happens to the expense line after it is processed?

  • A. Nothing significant results.
  • B. The actual cost is recorded at the portfolio level.
  • C. The actual amount incurred becomes part of the cost plan.
  • D. The cost plan closes.

Answer: C

 

NEW QUESTION 37
Which of the following are true regarding how the My Project Space (Project Workspace) handles dynamic content? (Choose two.)

  • A. If the project state is Pending or Open, planned start date and planned end date are displayed.
  • B. If the project state is On Hold, actual start date and actual end date are displayed.
  • C. If the project state is Draft, actual start date and actual end date are displayed.
  • D. If the project state is Work in Progress, actual start date and planned end date are displayed.

Answer: A,D

 

NEW QUESTION 38
What role can configure an idea module, map idea categories to the idea module, and add navigation for the Idea Portal?

  • A. Demand manager [it_demand_manager]
  • B. Project manager [it_project_manager]
  • C. Idea admin [idea_admin]
  • D. Idea manager [idea_manager]

Answer: C

 

NEW QUESTION 39
Which roles can modify agile properties? (Choose two.)

  • A. admin.
  • B. scrum_master.
  • C. it_pps_admin.
  • D. product_owner.

Answer: A,C

 

NEW QUESTION 40
Which of the following states appear in the process flow indicator at the top of the Demand form by default?
(Choose three.)

  • A. Updated
  • B. Draft
  • C. Screening
  • D. Approved
  • E. Deferred

Answer: B,C,D

 

NEW QUESTION 41
Who can submit Ideas?

  • A. Any IT user.
  • B. Any ITIL user.
  • C. Any user.
  • D. Any demand user.

Answer: C

 

NEW QUESTION 42
Demand managers can enhance a demand request by adding the following: (Choose three.)

  • A. Problems
  • B. Decisions
  • C. Requirements
  • D. Stakeholders
  • E. Change Requests

Answer: B,C,D

 

NEW QUESTION 43
To use the Time Sheet dashboard, what plugin must be installed?

  • A. Employee Service Center (com.sn_hr_service_portal)
  • B. Common ITSM Service Portal Application Components (com.snc.app_common.service_portal)
  • C. Performance Analytics - Content Pack - PPM Standard plugin (com.snc.pa.pmo_dashboards)
  • D. Knowledge Management - Service Portal (com.snc.knowledge_serviceportal)

Answer: C

 

NEW QUESTION 44
A project expense line is a cost associated with a specific source. Examples of specific sources could include:
(Choose three.)

  • A. Demand.
  • B. Project.
  • C. Fixed Asset.
  • D. Configuration Item (CI).
  • E. User.

Answer: C,D,E

 

NEW QUESTION 45
If the Agile Development 2.0 plugin is activated, an idea can be converted into which of the following task types? (Choose three.)

  • A. Epic
  • B. Project
  • C. SAFe feature
  • D. SAFe epic
  • E. Story

Answer: A,B,E

 

NEW QUESTION 46
The information displayed on Project Workspace is setup in which table?

  • A. pm_home_page_card
  • B. vtb_card
  • C. vtb_card_history
  • D. pm_project

Answer: A

 

NEW QUESTION 47
Where do you define 'Roles' requested via resource plans?

  • A. No need to define it differently, they are same are system roles
  • B. Resource roles under resource management.
  • C. Roles under system security
  • D. Under skill management modules

Answer: B

 

NEW QUESTION 48
The PPM Standard plugin enables an it_project_manager to perform the following activities: (Choose three.)

  • A. Define target for the portfolio
  • B. Establish resource requirements and track costs.
  • C. Track actual amount spent compared to an approved budget.
  • D. Configure cost type definition
  • E. Determine overall project cost requirements

Answer: B,C,E

 

NEW QUESTION 49
When creating a resource plan within a demand, how are the default dates on a resource plan determined?

  • A. Using demand created date
  • B. From portfolio date
  • C. Resource plan(s) cannot be created from demand
  • D. From demand start date and due date

Answer: D

 

NEW QUESTION 50
A customer requires five (5) teamspaces to support different departments. What should you do?

  • A. Activate via each teamspace plugin.
  • B. Enable the teamspace property.
  • C. Contact the Account Representative to activate the teamspaces.
  • D. Use UI Policies and Business Rules to enable teamspaces.

Answer: A

 

NEW QUESTION 51
The Project Portfolio Management application supports domain separation at this level:

  • A. Data only
  • B. Level 1 - Tenant data management
  • C. Level 3 - Tenant self-managed configuration
  • D. Level 2 - Tenant process management

Answer: A

 

NEW QUESTION 52
This should be updated by an it_pps_admin, so that the stakeholder list will automatically populate when a user creates a demand or project.

  • A. Stakeholder registry.
  • B. Application registry.
  • C. Demand form.
  • D. Project form.

Answer: A

 

NEW QUESTION 53
Which plugin provides a layer of artificial intelligence that empowers features and capabilities across applications to provide better work experiences?

  • A. Predictive Intelligence for PPM [com.snc.ppm_ml]
  • B. Strategic Spend Tracking for PPM [sn_ppm_sst]
  • C. Scenario Planning for PPM [sn_pw_scenario]
  • D. PPM Standard [com.snc.financial_planning_pmo]

Answer: A

 

NEW QUESTION 54
How is a resource group's capacity derived for resource planning?

  • A. Stored with Group Record.
  • B. Stored in Resource_Allocation_Daily table.
  • C. Aggregate capacity of all its members.
  • D. Stored in Resource_Aggregate_Daily table.

Answer: C

 

NEW QUESTION 55
......

Focus on CIS-PPM All-in-One Exam Guide For Quick Preparation: https://www.actualtestsquiz.com/CIS-PPM-test-torrent.html